Siemens S5 → S7-1500 PLC Migration
Legacy S5 migrated to S7-1500 in a planned shutdown. Every I/O mapped, new panel FAT-tested, zero surprises at startup.
Cement Plant E&I Cabling & Terminations
Cable ladder and tray at height, power and control pulling, motor-to-MCC terminations — in live plant conditions.
Fiber Optic Splicing & OTDR Certification
Fusion splicing and end-to-end OTDR certification — every link measured and documented down to the metre.
PLC Upgrade — Siemens S7-300
Full EPCC scope for Siemens S7-300 PLC upgrade. Panel fabrication, I/O wiring, programming, FAT and commissioning.
Siemens S5 → S7-300 Upgrade — Cement Plant
2,000+ I/O migrated on a combined marshalling + system panel, cut over inside a 5-day shutdown. Follow-on phases awarded.
Fitting Works
Cable fitting, glanding and termination works for cement industry client in Negeri Sembilan.
Cabling & Trunking
Full cabling trunking installation — cable tray, conduit and wiring for industrial facility.
Panel System
MCC and PLC control panel fabrication, installation and testing for cement production facility.
Cabling Works — O&G
Offshore and onshore cable installation works for oil and gas facility.
Remote Access & PLC Systems — PETRONAS Floating LNG
EPCC of ESXi remote access infrastructure + S7-400/Allen Bradley campaigns aboard PFLNG SATU & DUA.
Dilution Control System
Automated dilution water control system for palm oil mill CPO quality improvement.
Mill Automation — FGV Kilang Sawit Maokil
Digester level, chute door, VCT + skimmer and NIR dilution control. OER up 0.65pp in year one — verified by FGV lab records.